EVP: Project time line
Project Name | MBI0 Project Induction | MBI1 Kick Off | MBI2 Planning process defined | MBI3 Test Scripts developed CD Lab is Set up | MBI4 First Full CD deployment | Ad hoc reporting CI/CD based testing and bug fixing | MBI5 Second community validation lab fully setup | MBI6 BP deployed in second lab | Maturity Graduation Review by TSC (Request for graduation review made by PTL) | |
12/7/2019 | Target date | Mar 23, 2019 | Mar 29, 2019 | Apr 22, 2019 | May 03, 2019 | May 10, 2019 | May 17, 2019 | May 24, 2019 | May 31, 2019 | |
Achieved date | Mar 23, 2019 | Mar 29, 2019 |
|
|
|
|
|
|