Smart Data Transaction for CPS: Project time line

Smart Data Transaction for CPS: Project time line

 

Project Name

MBI0

Project Induction

 

MBI1

Kick Off

MBI2

Planning process defined

MBI3

Test Scripts developed

CD Lab is Set up

MBI4

First Full CD deployment

Ad hoc reporting

CI/CD based testing and bug fixing

MBI5

Second community validation lab fully setup

MBI6

BP deployed in second lab

Maturity Graduation Review by TSC

(Request for graduation review made by PTL)

Smart Data Transaction for CPS

 

Target date

11/01/2021

11/30/2021

12/20/2021

1/14/2022

 

1/31/2022

2/18/2022

After Akraino release7

Achieved date