Attendees
Agenda
- R3 review results - update
- R3 CI/CD logs - update
- Discuss development roadmap
- Use case
- PCEI Enabler functionality
- E2E Validation
- Allen and Gao to talk about validation lab ECM + CU
- Oleg to talk about validation lab at Equinix
- API engineering plan for R4 in November
Minutes
- Updated team on R3 review. PCEI was not accepted as an end-to-end blueprint due to lack of validation environment.
- cmti CA provided an update on CI/CD and security log generation
- gao chen Wei Chen Gao and Allen provided an overview of the CM/Tencent lab to be built
- Oleg Berzin provided an overview of the plan for the PCEI validation environment in the Equinix lab
- Equinix lab will have compute, interconnection, cloud access resources
- Equinix lab does not have 4G/5G network access. Options:
- Work with AT&T to enable 4G/5G access
- Use software simulation
- The team agreed to proceed with two validation labs (Equinix and Tencent/China Unicom)
- The team agreed to work on a common set of use cases in the two validation labs:
- UC1 - UPF Distribution
- UC2 - Local Break-out
- UC3 - Location Services