...
Meetings will be held bi-weekly on Mondays at 3 pm EST/EDT.
Feb 3, 2020
- haven't had a meeting in a little while & have stalled out a bit, as the key players setting up the new lab have left the project
- will look to have a meeting next week to start working up the plan to get this activity started up again
Jan 6, 2020
- attendees: Bruce, Bill, Alex
- first meeting for a while due to holidays
- Bruce let us know that the Intel GDC team has been re-assigned & will no longer be working on this blueprint - the work will be moved to another team, to be determined
- this is a late breaking development
- Bruce will follow up internally on the timing for identifying the new resources/lab to pick up the work that the GDC team was doing
Dec 2, 2019
- no meeting, didn't have quorum
Nov 25, 2019
- attendees: Abraham, Erich, Bruce, Glenn, Bill
- Erich & Abraham summarized their progress on installing a full Distribute Cloud in the GDC environment
- 2 controllers + 4 subclouds
- start with System Controller(s) - install from scratch
- currently Subclouds are not installed from scratch, but rather just added to the Cloud
- takes about 1.5 hours now, depending on how heavily loaded the network is
Nov 18, 2019
- did not have quorum for the meeting, likely due to holiday at GDC site
Nov 11, 2019
- meeting cancelled due to Remembrance Day
Nov 4, 2019
- attendees: Ada, Bill, Bruce
- work continues on GDC lab/Jenkins setup - team to provide an update by mid-week
Oct 28, 2019
- attendees: Ada, Bill, Bruce, Christopher L, Abraham
- per Christopher, they have started working on the DC install/config
- were able to establish subnet to subnet communication between System Controllers
- working on subcloud configuration now
- current forecast is to complete the install/config by Nov 15
Oct 21, 2019
- attendees: Ada, Bill, Bruce, Glenn
- SFEDC 2.0
- Ada's team will provide an updated estimate based on the information they've got now - by this Thursday
- Bill to fold the additional installation details into the overall distributed cloud documentation
- Bill to check if it's still possible to get into the overall 2.0 release if the blueprint 2.0 deliverables are completed some time in November
- Ada's team will provide an updated estimate based on the information they've got now - by this Thursday
- RFP-Ready Kit (RRK)
- a proof-of-concept kit to address an RFP
- something the IOTG group is using
- Glenn is interested in using the SFEDC 2.0 blueprint for their RRK
- IOTG would take this blueprint, and would apply it to their environment
Oct 7, 2019
- attendees: Bill, Ada, Bruce, Alex
- generally speaking, we are at risk for getting the 2nd lab set up by month's end - we'll continue to work towards that goal, the key items are as follows...
- Distributed Cloud Installation Recipe
- close, but not quite there - need an updated forecast from Yang on when this can be provided to Ada & team
- per Ada, this is for sure at risk now, since they haven't been able to start, and now need to assign a new resource to the activity (Haydeh is no longer on the project)
- Jenkins Information/Instructions
- per Ada, she has reviewed, the instructions look good - she will ask Christopher to review them as well - Ada will get a forecast from Christopher on setting this up
- Distributed Cloud Installation Recipe
...