Peng He

Chao Han

zhang zhenhuan

jin peng 

To be updated.

The maturity review process is shown in this page :BP Graduation Review Processes and Criteria

...

The collective TSC vote as defined in Akraino Technical Community Document#4.4.1TSCDecisionMakingProcess will be based on all the following set of checks being met:

...

IEC Type 5 SmartNIC successfully participated in Akraino release R3, R4 and R5's  incubation stage.


  • SW quality/functional check:

...

    1. Passing the mandatory set of test cases for all deployed layers using the tools and test set for each layer as defined by the Akraino Validation Framework Validation feature project (Akraino Blueprint Validation Framework) (after TSC approval). This will define minimum mandatory set of test that must be passed for each layer included in BP, plus
    2. Passing any additional test cases defined by the specific BP project as mandatory, plus
    3. Achieving the minimum Security requirements as defined by the Security subcommittee Steps To Implement Security Scan Requirements

  • HW definition check:
  • PCIe Backplane with 9 PCIe slots

  • One PCIe solt for SmartNIC

  • The other 8 PCIe slots for Edge Computing Server

...

       Upstream dependencies must be clearly defined

       DPDK version 20.11

       Open vSwitch 2.14.1

       LINUX Kernel 5.4

       SmartNIC BlueField 2

  • Documentation check:

Documentation subcommittee to provide a recommendation on graduation, or if not with items requiring action/remedy.

...

...