Akraino project reporting provides visibility of the each validation and feature project by means of a set of defined milestones terms MB1, MB2 etc.

The milestones are defined by the Documentation subcommittee.

Recording the milestones will be done by each project PTL so that the TSC can track project status.


1) Entry Criteria:  The project is approved to enter the incubation stage as per the TSC guideline (Akraino Project Reviews)

2) All milestones below may not apply to all projects and hence some may be marked optional after approval from TSC

3) Details of the Blue Print Milestones are in table below at the bottom of the page

4) There are sequential milestones (S) and non sequential milestones (NS). The non sequential milestones are guidelines to be completed at a certain stage, however they are not gating factors to enter the next stage. However the NS milestones also need to be completed at some point which will be marked as part of the relevant stage.


Project Name

MB0 Kick-Off

MB1

Planning complete

Identify integration/developers team & testing team

MB2

Integration Test plan created and shared with the community

Requirement/Feature Freeze (if applicable)

MB3

Scripts development and Set up accessible

Lab is set up for CD


MB4

Code Freeze (if applicable)

Test case development complete

MB5

first deployment in validation lab

first testing logs shipped

MB6

CI/CD based testing

Critical issues fixed.

Documentation complete (for third parties to recreate setup and run the tests)

Sign-Off (April 30th)

Release moved to mature

(Decision of completion made by PTL and TSC)

1SDN Enabled Broadband Access (SEBA) for Network Cloud Blueprint Familyx






2Serverless Blueprint Proposal for Addition to Network Cloud Blueprint Familyx






3

Unicycle Blueprint Proposal for Addition to Network Cloud Blueprint Family

x






4

Rover Blueprint Proposal for Addition to Network Cloud Blueprint Family

x






5OVS-DPDK Unicycle Dell Blueprint Proposalx






6

NC-TF-BluePrint-ProposalAkraino Network Cloud and TF Integration

x






7Edge Video Processingx






8

ELIOT IoT Gateway Blueprint

x






9

ELIOT SD-WAN/WAN Edge/uCPE Blueprint

x






10

IEC Type 1 for Integrated Edge Cloud (IEC) Blueprint Family

x






11IEC Type 2 for Integrated Edge Cloud (IEC) Blueprint Familyx






12

Industrial Edge (IE) Blueprint

x






13

Provider Access Edge (PAE) Blueprint

x






14

Radio Edge Cloud

x






15

StarlingX Far Edge Distributed Cloud

x






16

Time-Critical Edge Compute

x






17

Micro-MEC











Project Name

M0 Kick-Off

M1

Planning

M2

Functionality freeze

M3

API Freeze

M4

Code Freeze

RC0

Release Candidate 0

RC1

Release Candidate 1

RC2

Release Candidate 2

Sign-Off

Release Delivery


Project Name

M0 Kick-Off

M1

Planning

M2

Functionality freeze

M3

API Freeze

M4

Code Freeze

RC0

Release Candidate 0

RC1

Release Candidate 1

RC2

Release Candidate 2

Sign-Off

Release Delivery

17

Akraino Blueprint Validation Framework

x







18

Akraino Portal Feature Project

x







19

Cluster Health & Overload Monitoring Platform (CHOMP) Feature Project

x







20

Support of OVS-DPDK in Airship

x







MS

Name

Description/Checklist

MB0Blue Print Kick OffThe project is defined and approved to enter incubation stage (Incubation Review)
MB1Planning complete
  • Projects that have successfully completed MS0, must complete their planning, including scenario or deliverable definition.
  • As part of the planning process, all projects will complete a project planning template.
  • hardware set up definition frozen (NS)
  • Identify team working on features & testing (NS)
  • Paid Jenkins Set up (NS)
MB2

Integration Test plan created and shared with the community

Requirement/ Feature Freeze (if applicable)


  • Requirement/Feature freeze if there is code contribution as part of the blueprint or the upstream (All features are identified and JIRA stories created)
  • Comprehensive test plan documentation is created
  • hardware set up definition frozen ( NS)
  • Document the lab setup required and identify the labs that would be used to test this blueprint. If the lab is third party lab, get the lab reserved.
  • Security:<TBF>


MB3

Scripts development and Set up accessible

  • Make scripts available to create setups in third party labs.
  • Make the setups accessible for everybody (optional).
  • Instructions to access the setups. Method to reserve/un-reserve setups. Preferably two setups at-least.
  • Security: <TBF>
MB4

Code Freeze (if applicable)

Test case development complete



  • Integration complete of all SW packages that are part of the blueprint
  • All test cases are automated and made them available in blueprint repos.
  • Make the images available in public repository (Nexus?) and create scripts to necessary to install all SW packages in various sites as identified by blueprint


MB5

first deployment in validation lab

first testing logs shipped

  • All requirements uptill MB4 including NS ones should be complete at this stage
  • 1st run of test cases and results shared
  • All test cases planned for the release have been executed
  • Test results published
  • Failures and other issues have been documented
MB6

CI/CD based testing

Critical issues fixed.

Documentation complete (for third parties to recreate setup and run the tests)

  • Complete the documentation
  • Critical issues fixed
Sign-OffReleaseProjects tagged by PTLs using tagging procedure.