BP Incubation Stage Reporting R2

BP Incubation Stage Reporting R2

Rel 2 Incubation stage reporting

 MBI = Milestone Bp Incubation

1) Entry Criteria:  MBI0. The project is approved to enter the 'Incubation' stage after TSC review and approval (Akraino Project Reviews)

2) Details of the Blue Print Milestones are in the slide attached

3) A Blueprint can be part of Rel 2 as a self certified project by fulfilling MBI0-MBI4

4) Some Blueprints who were already part of Rel 1 may seek graduation review by fulfilling MBI0-MBI6

3) Even though Milestones come one after the other, they need not be sequential and are not gating factors to enter the next or a subsequent stage. 

4) It is to be noted that a blue print does not need to be mature to be part of rel2,  and more particularly if the Blue Print was not part of Rel1, it cannot be mature in Rel 2 since it would not be part of two releases in rel2

 

The self Certification/ maturity graduation reviews are done by assessing the projects against the Incubation or Mature review as defined in the Akraino Project Reviews page.

 

Note: Reporting of 'Achieved dates' are mandatory (if not optional milestones). The advance publishing of Target dates is optional.

 

Project Name

MBI0

Project Induction

 

MBI1

Kick Off

MBI2

Planning process defined

 

MBI3

CD Test Scripts developed

1st Validation Lab is Set up

Logs Linked to the wiki

 

MBI4

First Full CD deployment

BP is ready to download and deployable by users as self certified

Ad hoc reporting

CI/CD based testing and bug fixing

 

Ready for Rel 2 Incubation

Project Review

MBI5

Second community validation lab fully setup

MBI6

Ready for Maturity Review

Self Certification/Maturity Graduation Review as per BP Graduation Review Processes and Criteria

(Request for review made by PTL)

 

Project Name

MBI0

Project Induction

 

MBI1

Kick Off

MBI2

Planning process defined

 

MBI3

CD Test Scripts developed

1st Validation Lab is Set up

Logs Linked to the wiki

 

MBI4

First Full CD deployment

BP is ready to download and deployable by users as self certified

Ad hoc reporting

CI/CD based testing and bug fixing

 

Ready for Rel 2 Incubation

Project Review

MBI5

Second community validation lab fully setup

MBI6

Ready for Maturity Review

Self Certification/Maturity Graduation Review as per BP Graduation Review Processes and Criteria

(Request for review made by PTL)

1

uMEC

Dec 2018

Target date

2019-09-02

2019-09-11

2019-10-01

2019-10-15

 

 

 

 

 

Achieved date

2019-09-02

 

 

 

 

 

 

 

 

2

Network Cloud and TF Integration Project

Dec 2018

Target date

2018-12-31

2018-12-31

2019-10-01

2019-10-20

 

 

 

 

 

Achieved date

2018-12-31

 

 

 

 

 

 

 

 

3

Radio Edge Cloud (REC)

Dec 2018

Target date

2019-03-12

2019-05-20

2019-05-15

2019-05-30

 

 

2019-10-07

2019-10-31

 

Achieved date

2019-03-12

2019-05-28

2019-05-28

2019-05-28

 

 

2019-10-07

 

 

4

KNI Provider access edge

Jul 2019

Target date

2019-02-11

2019-04-30

2019-05-05

2019-05-30

2019-06-30

 

 

 

 

Achieved date

2019-02-11

2019-04-30

2019-05-03

2019-05-27

 

 

 

 

 

5

ICN

June 2019 

Target date

2019-05-03

2019-05-07

2019-10-15

2019-10-15

 

 

 

 

 

Achieved date

2019-05-03

2019-05-07

 

 

 

 

 

 

 

6

IEC Type 4: AR/VR oriented Edge Stack for Integrated Edge Cloud (IEC) Blueprint Family

Aug 2019 

Target date

2019-08-17

2019-11-11

 

 

 

 

 

 

 

Achieved date

2019-08-17

 

 

 

 

 

 

 

 

7

SDN Enabled Broadband Access (SEBA) for Telco Appliance Blueprint Family 

Dec 2018

Target date

2019-02-02

2019-10-14

2019-10-18

2019-10-25

 

 

 

 

 

Achieved date

2019-02-02

2019-10-30

2019-10-30

2019-10-30

 

 

 

 

 

8

Network Cloud Rover Blueprint

Dec 2018

Target date

 

 

 

 

 

 

 

 

 

Achieved date

2019-02-11

2019-04-29

2018-08-22

2018-08-22

2019-06-30

 

 

 

 

9

Network Cloud Unicycle with SR-IOV

Dec 2018

Target date

 

 

 

 

 

 

 

 

 

Achieved date

2019-02-11

2019-04-29

2018-08-22

2018-08-22

2019-06-30

 

 

 

 

10

StarlingX Far Edge Distributed Cloud

 

Target date

 

 

 

 

 

 

2019-10-30

 

 

Achieved date

 

 

 

 

 

 

 

 

 

11

IEC Type 2 & Type 1 for Integrated Edge Cloud (IEC) Blueprint Family

 

 

Target date

 

 

 

 

 

Sep 01, 2019

2019-11-08

 

 

Achieved date

Jan 28, 2019

Feb 05, 2019

Apr 2, 2019

https://jenkins.akraino.org/view/iec/

May 21, 2019

IEC Documentation

Jun 30, 2019

 

 

 

 

12

ELIOT SD-WAN/WAN Edge/uCPE Blueprint

Dec 2018

Target date

Feb 27, 2019

Apr 30, 2019

May 10, 2019

May 30, 2019

 

 

2019-10-30

 

 

Achieved date

Feb 27, 2019

Apr 30, 2019

May 10, 2019

May 30, 2019

Jun 30, 2019

 

 

 

 

13

ELIOT IoT Gateway Blueprint

Dec 2018

Target date

Feb 27, 2019

Apr 30, 2019

May 10, 2019

May 30, 2019

Jun 30, 2019

 

2019-10-30

 

 

 

14

AI/ML and AR/VR applications at Edge-

April 2019

Target date

April 25 2019

April 25 2019

Jul12th 2019

Setup on packet site

Jul12th 2019

Jul12th 2019

 

Oct 30th 2019

 

 

15

Connected Vehicle Blueprint

March 2019

Target date

March 2019

March 2019

Oct 15, 2019

Oct  20, 2019

Oct  25, 2019

Oct 30, 2019

 

 

 

16

ELIOT AIoT in Smart Office Blueprint

June 2019

Target date

Sept 2019

Oct 2019

 

 

 

 

 

 

 

17

Network Cloud Unicycle with OVS-DPDK

12/7/2019

Target date

Feb 8,2019

March 13,2019

May 3, 2019

May 30, 2019