BP Incubation Stage Reporting R1
Please go to R2 page for Rel 2 BP incubation Stage Milestone Reporting
PTL TSC Presentation Criteria
1) Is a validation lab in place?
2) Has a code repository been established?
3) Have regular meetings been scheduled?
4) Has a backlog been established?
5) Have any issues been identified that require support from the TSC?
Incubation stage reporting
MBI = Milestone Bp Incubation
1) Entry Criteria: MBI0. The project is approved to enter the 'Incubation' stage after TSC review and approval (Akraino Project Reviews)
2) All milestones below may not apply to all projects and hence some may be marked optional after approval from TSC
3) Details of the Blue Print Milestones are in table below at the bottom of the page
4) There are sequential milestones (S) and non sequential milestones (NS). The non sequential milestones are guidelines to be completed at a certain stage, however they are not gating factors to enter the next or a subsequent stage. However the NS milestones also need to be completed at some point which will be marked as part of the relevant stage.
The graduation reviews are done by assessing the projects against the Incubation to Mature review as defined in the Akraino Project Reviews page.
Note: Reporting of 'Achieved dates' are mandatory (if not optional milestones). The advance publishing of Target dates is optional.
Project Name | MBI0 Project Induction | MBI1 Kick Off | MBI2 Planning process defined | MBI3 CD Test Scripts developed 1st Validation Lab is Set up | MBI4 First Full CD deployment BP is ready to download and deployable by users as self certified | Ad hoc reporting CI/CD based testing and bug fixing | MBI5 Second community validation lab fully setup | MBI6 Ready for Maturity Review | Maturity Graduation Review as per BP Graduation Review Processes and Criteria (Request for graduation review made by PTL) | ||
---|---|---|---|---|---|---|---|---|---|---|---|
1 | SDN Enabled Broadband Access (SEBA) for Telco Appliance Blueprint Family | 12/7/2019 | Target date | Feb 2, 2019 | April 22, 2019 | May 30, 2019 | Jun 30, 2019 | ||||
Achieved date | Feb 2, 2019 | ||||||||||
2 | Serverless Blueprint Proposal for Addition to Network Cloud Blueprint Family | 12/7/2019 | Target date | ||||||||
Achieved date | |||||||||||
3 | 12/7/2019 | Target date | |||||||||
Achieved date | Feb 11, 2019 | Apr 29, 2019 | Aug 22, 2018 | Aug 22, 2018 | Feb 11, 2019 | ||||||
4 | 12/7/2019 | Target date | |||||||||
Achieved date | Feb 11, 2019 | Apr 29, 2019 | Aug 22, 2018 | Aug 22, 2018 | Feb 11, 2019 | ||||||
5 | 12/7/2019 | Target date | Feb 8,2019 | March 13,2019 | May 3, 2019 | May 30, 2019 | |||||
Achieved date | Feb 8,2019 | March 13,2019 | April 29, 2019 | May 26, 2019 | |||||||
6 | 12/7/2019 | Target date | |||||||||
Achieved date | |||||||||||
7 | 12/7/2019 | Target date | Mar 23, 2019 | Mar 29, 2019 | Apr 22, 2019 | May 30, 2019 | May 31, 2019 | ||||
Achieved date | Mar 23, 2019 | Mar 29, 2019 | |||||||||
8 | 12/7/2019 | Target date | Feb 27, 2019 | Apr 30, 2019 | May 10, 2019 | May 30, 2019 | |||||
Achieved date | |||||||||||
9 | 12/7/2019 | Target date | Feb 27, 2019 | Apr 30, 2019 | May 10, 2019 | May 30, 2019 | |||||
Achieved date | |||||||||||
10 | 12/7/2019 | Target date | Jan 28, 2019 | Feb 05, 2019 | Apr 15, 2019 | May 30, 2019 | Jun 30, 2019 | ||||
Achieved date | Jan 28, 2019 | Feb 05, 2019 | Apr 2, 2019 | May 21, 2019 | |||||||
11 | 12/7/2019 | Target date | Jan 28, 2019 | Feb 05, 2019 | Apr 15, 2019 | May 30, 2019 | Jun 30, 2019 | ||||
Achieved date | Jan 28, 2019 | Feb 05, 2019 | Apr 2, 2019 | May 21, 2019 | |||||||
12 | 12/7/2019 | Target date | Feb 11, 2019 | Apr 30, 2019 | May 5, 2019 https://jenkins.akraino.org/view/kni/ | Jun 30, 2019 | Jun 30, 2019 | ||||
Achieved date | Feb 11, 2019 | Apr 30, 2019 | May 3, 2019 | ||||||||
13 | 12/7/2019 | Target date | Feb 11, 2019 | Apr 30, 2019 | May 5, 2019 https://jenkins.akraino.org/view/kni/ | May 30, 2019 | Jun 30, 2019 | ||||
Achieved date | Feb 11, 2019 | Apr 30, 2019 | May 3, 2019 | May 27, 2019 | |||||||
14 | 12/7/2019 | Target date | 2019-03-12 | 2019-05-20 | 2019-05-15 | 2019-05-30 | 2019-05-10 | 2019-05-30 | |||
Achieved date | 2019-03-12 | 2019-05-28 | 2019-05-28 | 2019-05-28 | |||||||
15 | 12/7/2019 | Target date | 2019-03-04 | 2019-05-03 | 2019-05-28 | 2019-05-28 | |||||
Achieved date | 2019-03-04 | 2019-05-03 | 2019-06-04 | 2019-06-04 | |||||||
16 | 12/7/2019 | Target date | |||||||||
Achieved date | |||||||||||
17 | Target date | ||||||||||
Achieved date | |||||||||||
18 | 12/4/2019 | Target date | April 12, 2019 | June 12, 2019 | Sep 12, 2019 | Oct 12,2019 | |||||
Achieved date | |||||||||||
19 | 4/25/2019 | Target date | May 10, 2019 | June 6, 2019 | August 12, 2019 | October 12, 2019 | November, 12 2019 | TBD | TBD | ||
Achieved date | May 10, 2019 | ||||||||||
20 | |||||||||||
21 |
CHECK AND UPDATE TABLE BELOW ONCE MBIs AGREED
MBI | Name | Description/Checklist |
---|---|---|
MBI0 | Project Induction | Blue Print is voted by TSC as an Akraino Blueprint. The project is defined and approved by TSC vote to enter incubation stage (Incubation Review) |
MBI1 | Kick Off | First regular community call held, Recurring meeting should have been setup and details appear in the BP community meeting calendar: https://lists.akraino.org/g/blueprints/calendar. The first meeting date would be the timestamp for the 'Achieved date'. |
MBI2 | Planning Process Defined |
|
MBI3 | Additional Test scripts development CD lab is setup |
|
MBI4 | First Full CD deployment |
|
Ad hoc reporting | On going CI/CD Not really a milestone but an on going reporting period | Ad hoc reporting milestone is dependent on MBI6 Unlike the other milestones this milestone is a continuous one that spans from the start of testing (MBI6) as long as required by the CI/CD process until the BP is ready for the Maturing review by the TSC.
|
MBI5 | Second community validation lab fully setup |
|
MBI6 | BP successfully deployed in second community validation lab | All test cases planned for the release have been executed . Deployment in second lab may result in CI/CD iterations of the BP depending on results/experiences with the second setup. |
Maturity Graduation review | TSC conducts graduation review as per criteria set out in Remove This Page 2 | Request for graduation review made by PTL Decision of graduation made TSC TSC's Maturity Graduation review can have one of two outcomes:
|