Akraino project reporting provides visibility of the each BP validation project (MB1, MB2 etc) and feature project (MF1, MF2 etc) by means of a set of defined milestones.
The milestones are defined by the Documentation subcommittee.
BP validation projects milestones will be different in the 'Incubation' and 'Mature' stages since the graduation criteria from these two stages are different.
A single table shall be maintained for all projects in Incubation (i.e. tracking the progress towards graduating from Incubation to Mature)
A single table shall be maintained for all project in Mature stage (i.e. tracking the progress towards graduating Mature to Core)
Each project's PTL is responsibility for updating the table for their PTL so that the TSC can easily track project status.
Blueprint Validation Project reporting
Incubation stage reporting
1) Entry Criteria: MB0 The project is approved to enter the 'Incubation' stage after TSC review and approval (Akraino Project Reviews)
2) All milestones below may not apply to all projects and hence some may be marked optional after approval from TSC
3) Details of the Blue Print Milestones are in table below at the bottom of the page
4) There are sequential milestones (S) and non sequential milestones (NS). The non sequential milestones are guidelines to be completed at a certain stage, however they are not gating factors to enter the next stage. However the NS milestones also need to be completed at some point which will be marked as part of the relevant stage.
The graduation reviews are done by assessing the projects
Project Name | MB0 Kick-Off (Project inducted to 'Incubation' by TSC) | MB1 Planning complete Identify integration/developers team & testing team | MB2 Integration Test plan created and shared with the community Requirement/Feature Freeze (if applicable) | MB3 Scripts development and Set up accessible Lab is set up for CD | MB4 Code Freeze (if applicable) Additional test case development complete ( | MB5 First deployment in validation lab First test report logs shipped to LF CI servers | Ad hoc reporting CI/CD based testing Critical issues fixed. Documentation complete (for third parties to recreate setup and run the tests) | MB6 Second community validation lab identified | MB7 Second community validation lab fully setup | MB8 BP successfully deployed in second community validation lab | Graduation Review by TSC (Request for graduation review made by PTL) (Decision of graduation made TSC) TSC's Graduation review can have one of two outcomes:
| |
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | SDN Enabled Broadband Access (SEBA) for Network Cloud Blueprint Family | x | ||||||||||
2 | Serverless Blueprint Proposal for Addition to Network Cloud Blueprint Family | x | ||||||||||
3 | x | |||||||||||
4 | x | |||||||||||
5 | OVS-DPDK Unicycle Dell Blueprint Proposal | x | ||||||||||
6 | x | |||||||||||
7 | Edge Video Processing | x | ||||||||||
8 | x | |||||||||||
9 | x | |||||||||||
10 | x | |||||||||||
11 | IEC Type 2 for Integrated Edge Cloud (IEC) Blueprint Family | x | ||||||||||
12 | x | |||||||||||
13 | x | |||||||||||
14 | x | |||||||||||
15 | x | |||||||||||
16 | x | |||||||||||
17 |
Mature stage reporting
1) Entry Criteria: MB0 The project is graduated by the TSC from Incubation to Mature as per the TSC guideline (Akraino Project Reviews)
Project Name | MB0 Kick-Off (Project graduated from 'Incubation' to 'Mature' by TSC) | MB1 | ...... | Ad hoc reporting | ..... | Graduation Review by TSC (Request for graduation review made by PTL) (Decision of graduation made TSC) TSC's Graduation review can have one of two outcomes:
| |
---|---|---|---|---|---|---|---|
1 | SDN Enabled Broadband Access (SEBA) for Network Cloud Blueprint Family | ||||||
2 | Serverless Blueprint Proposal for Addition to Network Cloud Blueprint Family | ||||||
3 | |||||||
4 | |||||||
5 | OVS-DPDK Unicycle Dell Blueprint Proposal | ||||||
6 | |||||||
7 | Edge Video Processing | ||||||
8 | |||||||
9 | |||||||
10 | |||||||
11 | IEC Type 2 for Integrated Edge Cloud (IEC) Blueprint Family | ||||||
12 | |||||||
13 | |||||||
14 | |||||||
15 | |||||||
16 | |||||||
17 |
Feature Project reporting
Project Name | M0 Kick-Off | M1 Planning | M2 Functionality freeze | M3 API Freeze | M4 Code Freeze | RC0 Release Candidate 0 | RC1 Release Candidate 1 | RC2 Release Candidate 2 | Sign-Off Release Delivery | |
---|---|---|---|---|---|---|---|---|---|---|
Project Name | MF0 Kick-Off | MF1 Planning | MF2 Functionality freeze | MF3 API Freeze | MF4 Code Freeze | RC0 Release Candidate 0 | RC1 Release Candidate 1 | RC2 Release Candidate 2 | Sign-Off Release Delivery | |
17 | x | |||||||||
18 | x | |||||||||
19 | x | |||||||||
20 | x |
MS | Name | Description/Checklist |
---|---|---|
MB0 | Blue Print Kick Off | The project is defined and approved to enter incubation stage (Incubation Review) |
MB1 | Planning complete |
|
MB2 | Integration Test plan created and shared with the community Requirement/ Feature Freeze (if applicable) |
|
MB3 | Scripts development and Set up accessible |
|
MB4 | Code Freeze (if applicable) Test case development complete |
|
MB5 | first deployment in validation lab first testing logs shipped |
|
MB6 | CI/CD based testing Critical issues fixed. Documentation complete (for third parties to recreate setup and run the tests) |
|
Sign-Off | Release | Projects tagged by PTLs using tagging procedure. |