Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Blueprint Validation Project reporting

Incubation stage reporting

 MBI = Milestone Bp Incubation

1) Entry Criteria:  MBI0The project is approved to enter the 'Incubation' stage after TSC review and approval (Akraino Project Reviews)

2) All milestones below may not apply to all projects and hence some may be marked optional after approval from TSC

3) Details of the Blue Print Milestones are in table below at the bottom of the page

4) There are sequential milestones (S) and non sequential milestones (NS). The non sequential milestones are guidelines to be completed at a certain stage, however they are not gating factors to enter the next stage. However the NS milestones also need to be completed at some point which will be marked as part of the relevant stage.

The graduation reviews are done by assessing the projects 

...

Project Name

...

MBI0

Kick-Off

(Project inducted to 'Incubation' by TSC)

...

MBI1

Planning complete

Identify integration/developers team & testing team

...

MBI2

Integration Test plan created and shared with the community

Requirement/Feature Freeze (if applicable)

MBI3

Scripts development and Set up accessible

Lab is set up for CD

...

MBI4

Code Freeze (if applicable)

Additional test case development complete (

...

MBI5

First deployment in validation lab

First test report logs shipped to LF CI servers

...

Ad hoc reporting

CI/CD based testing

Critical issues fixed.

Documentation complete (for third parties to recreate setup and run the tests)

...

MBI6

Second community validation lab identified

...

MBI7

Second community validation lab fully setup

...

MBI8

BP successfully deployed in second community validation lab

...

Graduation Review by TSC

(Request for graduation review made by PTL)

(Decision of graduation made TSC)

TSC's Graduation review can have one of two outcomes:

  1. Project remains at 'Incubation' (i.e. the request to graduate wasn't approved by the TSC)
  2. Project graduates from 'Incubation' to 'Mature' (i.e. the request to graduate was approved by the TSC)


...

Unicycle Blueprint Proposal for Addition to Network Cloud Blueprint Family

...

Rover Blueprint Proposal for Addition to Network Cloud Blueprint Family

...

NC-TF-BluePrint-ProposalAkraino Network Cloud and TF Integration

...

ELIOT IoT Gateway Blueprint

...

ELIOT SD-WAN/WAN Edge/uCPE Blueprint

...

IEC Type 1 for Integrated Edge Cloud (IEC) Blueprint Family

...

Industrial Edge (IE) Blueprint

...

Provider Access Edge (PAE) Blueprint

...

Radio Edge Cloud

...

StarlingX Far Edge Distributed Cloud

...

Time-Critical Edge Compute

...

Micro-MEC

CHECK AND UPDATE TABLE BELOW ONCE MBIs AGREED

...

MBI

...

Name

...

Description/Checklist

...

  • Projects that have successfully completed MS0, must complete their planning, including scenario or deliverable definition.
  • As part of the planning process, all projects will complete a project planning template.
  • hardware set up definition frozen (NS)
  • Identify team working on features & testing (NS)
  • Paid Jenkins Set up (NS)

...

Integration Test plan created and shared with the community

Requirement/ Feature Freeze (if applicable)

  • Requirement/Feature freeze if there is code contribution as part of the blueprint or the upstream (All features are identified and JIRA stories created)
  • Comprehensive test plan documentation is created
  • hardware set up definition frozen ( NS)
  • Document the lab setup required and identify the labs that would be used to test this blueprint. If the lab is third party lab, get the lab reserved.
  • Security:<TBF>

...

Scripts development and Set up accessible

...

  • Make scripts available to create setups in third party labs.
  • Make the setups accessible for everybody (optional).
  • Instructions to access the setups. Method to reserve/un-reserve setups. Preferably two setups at-least.
  • Security: <TBF>

...

Code Freeze (if applicable)

Test case development complete

  • Integration complete of all SW packages that are part of the blueprint
  • All test cases are automated and made them available in blueprint repos.
  • Make the images available in public repository (Nexus?) and create scripts to necessary to install all SW packages in various sites as identified by blueprint

...

first deployment in validation lab

first testing logs shipped

...

  • All requirements uptill MB4 including NS ones should be complete at this stage
  • 1st run of test cases and results shared
  • All test cases planned for the release have been executed
  • Test results published
  • Failures and other issues have been documented

...

CI/CD based testing

Critical issues fixed.

Documentation complete (for third parties to recreate setup and run the tests)

...

  • Complete the documentation
  • Critical issues fixed

...

Mature stage reporting

 MBM = Milestone Bp Mature

...